Railroad Grade Separation
Program
|
|||||||||||
| Dist. | Project | PID | Project Sponsor |
Rail Carrier |
Rough Project Cost |
Description/Comments |
Feasibility Study | 2003 | |||
|
2 |
Wood - Wales Road/Vickers Xing |
23113 |
Northwood |
CSXT, NS |
$ 8.0 |
Feasibility study complete. Railroad Alternative = $30 m; Roadway Alternative = $10.6 m. Stakeholder Review |
Completed |
||||
|
2 |
Seneca - Jones Road |
23111 |
Fostoria |
CSXT |
$ 4.5 |
TAG preparing feasibility study. |
01/30/03 |
||||
|
2 |
Lucas - Summit Street |
23117 |
Toledo |
CSXT |
$ 10.0 |
District 2 analyzing options for incorporation with Greenbelt Parkway. |
Completed |
||||
|
2 |
Fulton - Hallet Avenue |
23114 |
Swanton |
NS |
$ 7.0 |
TAG preparing feasibility study. |
01/30/03 |
||||
|
2 |
Wood - Oregon Road |
23115 |
Wood County |
CSXT |
$ 6.0 |
TAG preparing feasibility study. |
01/10/03 |
||||
|
3 |
Erie - U.S. 6/S.R. 101 |
23105 |
Sandusky |
NS |
$ 9.5 |
Controversal issues, hold in Tier II pending completion of environmental process. |
Completed |
||||
|
3 |
Lorain - S.R. 58 |
23104 |
Wellington |
CSXT |
$ 10.4 |
Feasibility study has been completed. Complete Environmental, then reevaluate. |
Completed |
$ 650,000 |
|||
|
3 |
Huron - U.S. 250 |
23109 |
Greenwich Twp. |
CSXT |
?? |
TAG preparing feasibility study. |
12/30/02 |
||||
|
4 |
Ashtabula - Austin Road |
23061 |
Geneva |
CSXT |
$ 7.0 |
Feasibility study completed and accepted by TAG. Complete Environmental, then reevaluate. |
Completed |
$ 200,000 |
|||
|
4 |
Summit - Highland Road |
23064 |
Macedonia |
NS |
$ 5.2 |
TAG to review feasibility study upon completion by sponsor. |
02/15/03 |
||||
|
4 |
Ashtabula - West Avenue |
23062 |
Ashtabula |
NS |
$ 7.0 |
Feasibility study has been completed. Complete Environmental, then reevaluate. |
Completed |
$ 150,000 |
new |
||
|
Studies to be Initiated in 2003 |
|||||||||||
|
1 |
Defiance - Hire Road |
Defiance County |
CSXT |
?? |
TAG to perform feasibility study of proposed project. To be initiated in early 2003. |
2003 |
|||||
|
3 |
Huron - S.R. 13 |
23108 |
Greenwich Twp. |
CSXT |
?? |
TAG to perform feasibility study of proposed project DOT # 518485H. |
2003 |
||||
|
6 |
Delaware - Home Road |
Delaware County |
CSXT |
$ 3.4 |
TAG to review feasibility study upon completion by sponsor. |
2003 |
|||||
|
8 |
Hamilton - Reading Road |
Sharonville |
NS |
?? |
TAG to perform feasibility study of proposed project. |
2003 |
|||||
|
Total |
$ 94 |
Previous Tier II Commitments |
$ 1,759,000 |
||||||||
|
New Tier II Commitments |
$ 150,00 |
||||||||||
|
Note1: For projects of unknown cost, rough estimates of
$3 million and $7 million were used for rural and urban locations
respectively.
Note2: For Wood-Wales Road/ Vickers Crossing, a maximum TRAC commitment of $8.0 million was assumed. Note 3: This list reflects the removal of the Hudson and Marion projects due to lack of feasibility. For details concerning the feasibility studies, contact the program manager at 614-466-1267. Note 4: Previous Tier II commitments include FY 2002 expenditures and FY 2003 expenditures on projects that have been moved to Tier I. |
|||||||||||