TRAC Home | Tier I Draft List | Complete Draft List in PDF format
| 2001-2007 Major New
Construction Program Preliminary Draft Recommendations Tier II - Projects to Be Continued for Some Stage of Development December 20, 2002 |
|||||||||
| The following list explains the project development activities for the Tier II Major New Construction Projects. | |||||||||
|
|||||||||
|
Dist. |
Project |
PID |
Cost |
Demo |
Commitment |
Description |
2003 |
2004 |
2005 |
2006 |
2007 |
|||
|
Proposed New Tier II Funding Commitments |
||||||||||||||
|
2 |
Lucas I-75/I-475 |
23648 |
$30.0 |
|
$3.0 |
Upgrade Interchange of I-75 and I-475 Phase 1 |
|
$3.0 |
||||||
|
2 |
Lucas I-475 |
19119 |
$61.0 |
$6.0 Local R/W |
$0.9 |
Upgrade Interchange of I-475 and Salisbury Road |
|
$0.9 |
||||||
|
7 |
Montgomery I-75 |
22357 |
$400.0 |
$1.8 SPR |
$14.0 |
Upgrading I-75 in Downtown Dayton |
|
$11.0 |
||||||
|
8 |
Hamilton/Warren US 22 |
No PID |
$51.0 |
$2.0 County |
$6.0 |
Widen US 22/3 from two to five-lanes |
$2.0 |
$4.4 |
|
|
|
|||
|
10 |
Hocking/Athens US 33 |
14040,23846 |
$58.5 |
|
$9.0 |
Nelsonville Bypass, Phase I |
$2.5 |
|
|
|
|
|||
|
10 |
Hocking/Athens US 33 |
14040 |
$50.0 |
|
$0.8 |
Nelsonville Bypass, Phase II |
|
$0.8 |
|
|
|
|||
|
10 |
Washington SR 7 |
?? |
$23.7 |
|
$0.4 |
Improve SR 7 on the eastside of Marietta |
|
$0.4 |
|
|
|
|||
|
11 |
Stark/Columbiana US 30 |
20344 |
$42.0 |
|
$6.0 |
Relocate US 30 from Trump Ave. to SR 44 |
|
$3.6 |
2.5 Pre. Committed |
|||||
|
Previous Tier II Projects |
$4.5 |
$24.1 |
$0.0 |
$0.0 |
|
|||||||||
|
1 |
Defiance/Henry US 24 |
19047 |
$36.0 |
$5.7 Demo |
$0.9 |
Widen US 24 from Defiance to Napoleon |
|
$0.9 |
|
|
|
|||
|
1 |
Paulding/Defiance US 24 |
18904 |
$115.0 |
$5.7 Demo |
$2.0 |
Widen US 24 from Indiana to Defiance |
|
$2.0 |
||||||
|
1 |
Hancock US 30 |
12421 |
$23.1 |
$ RW Demo |
$0.7 |
Relocate US 30 from US 68 to SR 37 |
Right-of-way completed awaiting construction |
|||||||
|
1 |
Hancock US 30 |
12420 |
$39.3 |
$ RW Demo |
$0.8 |
Relocate US 30 from SR 235 to US 68 |
Right-of-way completed awaiting construction |
|||||||
|
1 |
Hancock/Wyandot US 30 |
12422 |
$50.8 |
$ RW Demo |
$0.3 |
Relocate US 30 from SR 37 to Upper Sandusky |
Right-of-way completed awaiting construction |
|||||||
|
2 |
Henry/Lucas US 24 |
20404 |
$153.4 |
$5.7 Demo |
$20.0 |
Widen US 24 from Napoleon to Waterville |
|
$9.6 |
$10.0 |
|
||||
|
2 |
Wood I-75 |
23890 |
$9.2 |
|
|
New Interchange at I-75 north of Bowling Green |
Awaiting completion of Interchange Justification Study |
|||||||
|
2 |
Wood/Sandusky US 20 |
23312 |
$23.0 |
|
$1.8 |
Widen US 20 from SR 420 to Lime St. in Woodville |
$1.8 |
|
|
|
|
|||
|
3 |
Sandusky/Huron US 20 |
12061 |
$30.0 |
|
|
Bypass of Bellevue |
Studying alternative solutions |
|||||||
|
4 |
Akron Metro CAC Rail |
|
$250.0 |
|
|
Canton-Akron-Cleveland Commuter Rail project |
MIS resulting projects to come to TRAC 2003 |
|||||||
|
4 |
Columbiana/Mahoning SR 14 |
12122 |
$33.0 |
|
|
Phase 3 of US 62 relocation - new four-lane |
Review Environmental Documents |
|||||||
|
4 |
Mahoning/Trumbull US 62 |
9566 |
$45.3 |
|
$2.7 |
Hubbard Expressway - Arterial alternative US 62F to I-80 |
|
$2.7 |
|
|
|
|||
|
4 |
Stark/Columbiana US 62 |
4089 |
$59.8 |
|
|
New limited access four-lane from Salem to Alliance |
Review Environmental Documents |
|||||||
|
4 |
Summit I-77 |
16514 |
$45.1 |
|
$1.0 |
Widen I-77 from SR 162 (Copley Rd) and SR 21 |
$1.0 |
|
|
|
|
|||
|
4 |
Summit I-77 |
16372 |
$31.1 |
|
$2.3 |
Widen I-77 from Airport Interchange to SR 241 |
$1.4 |
|
|
|
|
|||
|
4 |
Summit SR 8 |
24507,24508 |
$104.3 |
$1 County |
$10.7 |
Convert roadway to a four-lane limited access from SR 303 to I-271 |
$10.2 |
Design and R/W |
|
|
|
|||
|
4 |
Summit SR 8 |
11661 |
$6.0 |
$3.0 City |
|
New Interchange SR 8 at Seasons Rd. |
Local Pursuing further development |
|||||||
|
5 |
Franklin/Fairfield US 33 |
23152 |
$135.0 |
|
$5.0 |
Upgrade US 33 Columbus to Lancaster to interstate standards |
Complete Preliminary Engineering |
|||||||
|
5 |
Franklin/Licking SR 161/SR 37 |
12139 |
$42.4 |
First phase only |
$10.6 |
Widen SR 161/SR 37 to four lanes to connect Newark and Columbus |
$5.0 |
$3.6 |
|
|
|
|||
|
5 |
Muskingum - SR 93 |
20428 |
$18.8 |
$0.5 High Priority |
|
SR 93 / 22 Connector |
Preliminary development |
|||||||
|
6 |
Franklin I-670 Intl. Gateway |
75293 |
$39.3 |
$15 Airport |
$1.5 |
Upgrade the Stelzer/Intl. Gateway intersection to a interchange |
$1.5 |
|
|
|
|
|||
|
6 |
Franklin ITS |
No PID |
$43.0 |
|
|
Columbus ITS |
Currently Under Design |
|||||||
|
6 |
Franklin/Delaware North Rail |
75306 |
$433.7 |
|
$2.5 |
New Passenger Rail facility from downtown to Polaris |
$2.5 |
|
|
|
|
|||
|
7 |
Champaign US 68 |
9927 |
$19.0 |
$3.0 County/City |
|
Bypass of Urbana |
Awaiting completion of environmental studies |
|||||||
|
7 |
Montgomery I-75 |
10697 |
$80.0 |
|
|
Build a new interchange in southern Montgomery County near Austin Rd. |
Locals Completing IJS |
|||||||
|
8 |
Butler I-75/SR 63 |
10752 |
$44.5 |
|
$2.3 |
Reconstruct and expand I-75/SR 63 Interchange |
Environmental/Design previously funded |
|||||||
|
8 |
Butler SR 63 |
No PID |
$0.2 |
$0.2 County |
|
Oxford to Monroe corridor improvement study |
Locals Performing Corridor Study |
|||||||
|
8 |
Clermont I-275/SR 32 |
22972 |
$0.5 |
|
$0.5 |
Upgrade the I-275 and SR 32 Interchange area |
Complete Preliminary Engineering |
|||||||
|
8 |
Eastern Corridor Study |
No PID |
$22.0 |
$5.0 |
$4.4 |
Improve the East/West movement on the east side of Cincinnati |
$2.7 |
|
|
|
|
|||
|
8 |
Hamilton I-71 Transit Corridor |
19139 |
$539.7 |
$65 Locals/FTA |
$7.0 |
Ohio portion of Ohio-Kentucky LRT ( light rail transit) |
Preliminary Engineering funded |
|||||||
|
8 |
Hamilton I-74 |
21146 |
$11.0 |
|
|
Widen New Haven Rd. Bridge and interchange ramps |
Locals Developing Project |
|||||||
|
8 |
Warren I-75 |
No PID |
?? |
|
|
New Interchange on I-75 at Greentree |
Awaiting completion of Interchange Justification Study |
|||||||
|
9 |
Ross SR 104 |
21250 |
$9.8 |
|
|
Widen SR 104 from US 35 to SR 207 |
Locals Developing Project |
|||||||
|
12 |
Cuyahoga Central Viaduct/Innerbelt Study |
|
$400.0 |
$6 District |
|
Needs study of the downtown Cleveland interstates |
District funding Feasibility Study |
|||||||
|
12 |
Cuyahoga I-77 |
22222 |
$34.3 |
|
$2.5 |
Widen I-77 from SR 82 to Pleasant Valley Rd. |
$2.5 |
|
|
|
|
|||
|
|
|
|
|
|
|
|
$33.1 |
$42.9 |
$0.0 |
$10.0 |
$0.0 |
|||