CHRISTMAS AND
NEW YEAR’S HOLIDAY TRAFFIC UPDATE
COLUMBUS (December 20, 2007) –
The Ohio Department of
Transportation (ODOT) knows the coming holidays will be a busy time
for the state’s roads and highways. The department expects holiday
traffic to be at its peak the Saturday before Christmas, when Ohio’s
rural highway traffic volumes could increase by 41 percent over the
typical monthly average.
ODOT reminds motorists
that during these winter months, travel conditions can change from mile
to mile, minute to minute. Before leaving home, find out the latest
driving conditions by logging on to
www.BuckeyeTraffic.org. Safe
drivers know the weather and their limits. If the weather is bad,
remember, Ice and Snow…Take it Slow.
While work is suspended in
many of the state’s construction zones during this time, lane
restrictions or detours may still affect your holiday commute. Where
possible, ODOT opens additional lanes of traffic and requires
contractors to maintain at least two lanes of traffic in each direction
on Ohio’s interstates. To aid motorists, ODOT is providing this
comprehensive list of major state construction projects.
Select construction overview information by regions of
Ohio:
| Central | Eastern |
Northeast | Northwest |
| Southwest
| Southern | Southeast | Western |
|
.
|
|
Northwest Ohio
U.S. Route 20, Sandusky and Wood counties
U.S. 20 is being widened from two lanes to five from Pine St. in
Woodville to the U.S. 20/SR 420 interchange. Westbound and eastbound
lanes are reduced to 11 feet with a restriction of eight feet, six
inches currently in effect throughout the construction zone. One lane
in both directions will be maintained at all times. While the work
zone restrictions remain in place, work is suspended over the holiday
and there will be no additional lane closures until Jan. 21, 2008.
Completion date: mid-November 2009.
U.S. Route 24, Defiance and Henry counties
Widening and reconstruction of U.S. 24 between the city of Napoleon
and the city of Defiance. Some lane restrictions will be required, but
traffic on U.S. 24 is maintained at all times. Traffic is now four
lanes from just east of SR 66 to just east of Domersville Rd. The
interchange with SR 281 and U.S. 24 is now open. Completion date: fall
2008.
U.S. Route 24, Defiance County
The reconstruction of the existing two lanes of U.S. 24 and the
construction of two additional lanes to expand the route to a
four-lane highway. The existing four-lane section from SR 15 to SR 66
is reduced to one lane in each direction. Traffic is switched into the
new westbound lanes between the U.S. 24 bypass and SR 424 to allow for
construction of the new eastbound lanes. Completion date: November
2008.
State Route 25, Wood County
SR 25, from Roachton Rd. to Front St., has intermittent lane
restrictions between 7 a.m. and 4 p.m. daily until the end of January
to install traffic signal poles and traffic signals. Two-way traffic
will be maintained with flaggers. Minor delays possible. Work will be
suspended over the holiday. Completion date: Jan. 15, 2007.
Interstate 280, Lucas County
Construction of the Veterans’ Glass City Skyway Bridge over the Maumee
River on I-280. The new bridge is open to three lanes of traffic in
each direction. While intermittent lane closures will continue through
December for finishing activities, work is suspended over the holiday
and there will be no additional lane closures. Completion date: summer
2008.
Interstate 280, Lucas County
Work crews are planting trees and preparing planting beds along the
right shoulders in both directions on I-280, between Navarre and
Manhattan, from 7 a.m. until 4 p.m. daily. No lane closures are
anticipated, but motorists should be aware of workers near the roadway
and of possible shoulder closures. Completion date (Estimated):
October 31, 2009 (weather permitting).
State Route 576, Williams County
SR 576 is closed south of Montpelier, between U.S. 6 and SR 34 in
Williams County due to culvert failure. Detour is posted. Due to the
nature of the project, the completion date is unknown at this time.
Visit this link for details:
http://www.odotonline.org/detours/detour.asp?detNumber=509
|
|
..top
|
|
Northeast Ohio
State Route 8, Summit County
Reconstruction of SR 8 from south of Twinsburg
Rd. to north of the I-271 interchange. Two lanes of
traffic in each direction will be maintained on SR 8
at all times. Twinsburg Rd. at SR 8 is closed, and
will reopen as an underpass in late fall 2009. While
the permanent work zone restrictions remain in
place, work is suspended over the holiday and there
will be no additional lane closures. Detours are
posted. Completion date: summer 2010.
State Route 19, Crawford County
SR 19, one-half mile north of Albaugh Rd. in
Lykens Township, is closed for an unanticipated
embankment repair project. Detour is posted. The
project includes underground geotechnical work. ODOT
crews are testing and studying the area by drilling
to discover the extent of the situation and develop
a remediation plan. Due to the nature of the
problem, a completion date cannot be given at this
time. The closure will remain in place until the
scope of this problem is determined and a solution
is implemented.
U.S. Route 20, Lake County
Widening and reconstruction on U.S. 20, from the
Mentor corporation line to the Painesville
corporation line. One lane of traffic in each
direction is maintained on U.S. 20 at all times.
Permanent work zone restrictions remain in place
over the holidays. Completion date: summer 2008.
Interstate 77, Stark County
Widening and reconstruction on I-77 from W.
Tuscarawas St. (SR 172) to 13th St. A minimum of two
lanes of traffic are maintained in each direction on
I-77. Completion date: June 2008.
Interstate 77, Summit County
Widening and reconstruction on I-77 from Copley
Rd. (SR 162) to Cleveland-Massillon Rd. in the
cities of Akron and Fairlawn, and in Bath and Copley
townships. A minimum of two lanes of traffic are
maintained in each direction on I-77 through
construction. Completion date: fall 2008.
Interstate 80, Mahoning County
Widening the roadway and construction of new
twin bridges over the Meander Reservoir on I-80,
between SR 45 and the SR 11 interchange. Two lanes
of traffic are maintained in each direction. While
the permanent work zone restrictions remain in
place, work is suspended over the holiday and there
will be no additional lane closures. Completion
date: fall 2009.
Interstate 271, Summit County
I-271 over SR 8 is reduced to one through lane and
one exit only lane in each direction as part of the
SR 8/I-271 reconstruction project. While the
permanent work zone restrictions remain in place,
work is suspended over the holiday and there will be
no additional lane closures. Completion date: summer
2010.
Interstate 271, Summit County
I-271 over the Cuyahoga River in Boston Township is
reduced to one lane in each direction during off
peak hours for major reconstruction. This work is
part of a $33 million project for replacing the
I-271 twin bridges over the Cuyahoga River and the
Cuyahoga Valley National Park. Completion date: fall
2009.
State Route 283, Lake County
Reconstruction of SR 283 between SR 615 (Munson Rd.)
and Washington Ave. One lane of northeast traffic is
maintained. Detours are posted for traffic traveling
in the southwest direction. While the permanent work
zone restrictions remain in place, work is suspended
over the holiday. Completion date: October 2008.
U.S. Route 322, Cuyahoga County
Widening and reconstruction of U.S. 322 (Mayfield
Rd.) between Lander Rd. and the eastern Mayfield
Heights corporation limit. Construction currently
takes place between Wal-Mart Dr. and the eastern
Mayfield Heights corporation limit only. Traffic is
maintained throughout the project’s limits. Left
turns are permitted only at signalized
intersections. While permanent work zone
restrictions remain in place, work is suspended over
the holiday. Completion date: fall 2009.
U.S. Route 422, Geauga County
Reconstruction of U.S. 422, including four driving
lanes and a center turn lane between SR 88 and the
Portage County line in Parkman and Nelson townships.
Eastbound traffic is maintained. Westbound traffic
will be detoured for the duration of the project.
Detours are posted. Permanent work zone restrictions
remain in place over the holiday. Completion date:
fall 2008.
|
|
..top
|
|
Western Ohio
U.S. Route 35, Montgomery County
Major repair and replacement of roadway and bridges,
from I-75 to just east of the current Steve Whalen
Blvd. exit. Two lanes of traffic are open in the
westbound direction. Three lanes are open in the
eastbound direction. Traffic is shifted on U.S. 35
westbound, where there are 10-foot, 6-inch lane
width restrictions in place. The U.S. 35 eastbound
ramp to Keowee St. is closed within the work zone.
Motorists should expect congestion and delays. While
the permanent work zone restrictions remain in
place, work is suspended over the holiday and there
will be no additional lane closures. Detours are
posted. Completion date: spring 2008.
Interstate 70/Huber Heights,
Montgomery County
Work continues on I-70 from the I-70/I-75
interchange to east of the Clark County line for the
reconstruction and widening of I-70. Two lanes of
traffic are maintained in each direction. Motorists
should use caution and reduce their speed through
this area. Expect congestion and possible delays.
The I-70 eastbound off ramp and the I-70 westbound
on ramp at SR 201 will be closed until mid-December,
follow the detour signing as provided. While the
permanent work zone restrictions remain in place,
there will be no additional lane closures over the
holiday. Completion date: summer 2008.
Interstate 70/Interstate 75,
Montgomery County
Reconstruction continues at the I-70/I-75
interchange just north of Dayton. Two lanes of
traffic are maintained in each direction on I-70
through the interchange. I-75 is reduced to two
lanes in each direction between U.S. 40 and just
south of I-70. Motorists should use caution and
reduce their speed through this area. Expect
congestion and possible delays. While the permanent
work zone restrictions remain in place, there will
be no additional lane closures over the holiday.
Completion date: summer 2009.
Interstate 75, Montgomery County
Phase 1A of the modernization of I-75 through
downtown Dayton. Work is being performed during
daylight hours from Stanley Ave. south to Main St.
The following ramps have been permanently closed:
Grand Ave. to I-75 northbound; Grand Ave. connector
to Main St.; and I-75 southbound to Leo / Keowee St.
exit. Shaw Ave. is open to local traffic only. There
will be no lane closures in effect during the
holiday. Completion date: June 2011.
|
|
..top
|
|
Central Ohio
State Route 161, Licking County
A major expansion project on SR 161, including
several road alignment changes, from east of New
Albany to Newark. Traffic will be maintained on one
lane of two-way traffic with temporary traffic
signals and flaggers. The speed limit has been
reduced to 45 miles per hour. Traffic will be slowed
during the holiday weekend due to the construction
and to several county and township roads closed
along the route. Completion date: October 2009.
Interstate 270, Franklin County
Major reconstruction of the I-71 and I-270
interchange on the north side of Columbus. All lanes
are open. Work is suspended over the holiday and
there will be no lane closures. Completion date: May
2008.
Interstate 270/State Route 161,
Franklin County
Major reconstruction of the SR 161 interchanges at
I-270 and Sunbury Rd. on the northeast side of
Columbus. Traffic patterns, ramps and signals have
changed significantly. The speed limit on SR 161
westbound at Sunbury Rd. is reduced to 45 mph. While
the permanent work zone restrictions remain in
place, work is suspended for the holiday and there
will be no additional lane closures. Completion
date: June 2008.
|
|
..top
|
|
Eastern Ohio
State
Route 170, Columbiana County
Reconstruction and widening from just west of CR 447
to just south of CR 430 in Calcutta. To minimize
traffic delays caused by this work and inconvenience
to motorists, construction on SR 170 is only taking
place between the hours of 7 p.m. and 7 a.m. Traffic
is being maintained in both directions on the route,
however, motorists are advised to use an alternate
route and asked to exercise caution through this
area. Completion date: June 2008.
|
|
..top
|
|
Southwest Ohio
U.S. Route 22 and State Route 3,
Hamilton and Warren counties
Widening of Montgomery Rd. (U.S. 22 and SR 3) from
Cornell Rd. to Appleseed Rd. in Hamilton County to
increase capacity and improve safety. One lane of
traffic in each direction north of Kemper Rd. is
being maintained. Work is suspended over the
Christmas holiday weekend. Completion date: fall
2008.
U.S. Route 50, Hamilton County
Widening of U.S. 50 from just east of the Mariemont
east corporation line to just east of Newtown Rd.
The work includes widening the existing pavement for
a center turn lane, and lengthening the right turn
lane approaching Newtown Rd. One lane of traffic in
each direction is being maintained. While the
permanent work zone restrictions remain in place,
work is suspended during Christmas week and there
will be no additional lane closures. Completion
date: May. 31, 2008.
State Route 73, Clinton County
To accommodate construction of the Wilmington
Bypass, SR 73 is closed just southeast of the
intersection with Airport Rd. until May 8, 2008.
Traffic is not permitted to turn right from Airport
Rd. onto SR 73. Detour is posted. Completion date:
fall 2010.
Interstate 275, Hamilton County
Rehabilitation of the roadway, pavement and 28
bridge structures on I-275 from just east of Winton
Rd. to just east of U.S. 42. Work includes adding a
fourth lane in both directions, widening the
eastbound and westbound on and off ramps to
Mosteller Rd., and replacing the bridge deck s on
the Chesterdale and U.S. 42 overpasses. During peak
travel hours, three lanes of traffic on I-275
maintained in each direction. To maintain these
three lanes, ODOT is shifting one lane of eastbound
traffic onto the westbound side of I-275 to create
an express lane through the work zone. Tractor
trailers are prohibited in this lane, and there are
no exits until the lane joins with mainline I-275.
During the project’s second phase, this lane carries
eastbound traffic from just east of the Winton Rd.
interchange to just east of U.S. 42. While the
permanent work zone restrictions remain in place,
work is suspended through Jan. 1 and there will be
no additional lane closures. Completion date: fall
2010.
|
|
..top
|
|
Southern Ohio
State Route 551, Pike County
SR 551 is closed at the Pee Pee Creek Bridge in the
Lake White Region, just south of SR 220, due to
damage incurred by flooding. The bridge is closed
until further notice, and motorists are being
detoured via SR 552.
|
|
..top
|
|
Southeastern Ohio
State Route 124, Athens County
SR 124, just south of the Washington County line, is
closed due to a significant slip. This is a
permanent closure. SR 144 may be used as a detour
until such time that a new state route is
established.
|
|
..top
|
For Further Information contact: