Columbus Crossroads, ODOT I-70/I-71 South Innerbelt Study

 

Ohio Department of Transportation  

I-270 Columbus North Central Outerbelt Study >> Project Overview >> Preliminary Recommendations (Summary), Feb. 2004

 

Preliminary Recommendations (Summary)

Preliminary Recommendations (Summary)

I. Introduction
Over the past several months, the Ohio Department of Transportation has been conducting an analysis of eight concepts that may help reduce accidents and congestion on the Interstate 270 North Central Outerbelt between State Route 315 and Interstate 71.

The concepts were identified and evaluated based on input from the public and an Advisory Committee made up of community and business representatives. The evaluation criteria placed importance on reducing congestion and accidents, minimizing environmental and community impacts and maximizing cost effectiveness.


II. Background
Today, the North Central Outerbelt in Columbus is the fourth most congested, high-crash freeway location in Ohio – serving about 180,000 vehicles per day and experiencing 542 accidents per year.

The interchanges at S.R. 315, U.S. 23 and I-71 were built in the ‘60s and serve about 10 to 20 percent more traffic than they were designed to handle. The outdated design and the close proximity of interchanges, particularly at S.R. 315 and U.S. 23, cause excessive driver weaving and merging that create congestion during peak hours and contribute to hundreds of accidents each year.

About 36 percent of all crashes occur during the evening rush hours between 3 p.m. and 7 p.m. and 42 percent of the crashes are rear-end collisions, which is typical of stop-and-go traffic.


III. Summary of Recommendations

State Route 315 Interchange
Recommended: Replace "loop" ramps with flyover ramps that reduce weaving and merging.

ODOT recommends Alternative 1, which would replace loop ramps at S.R. 315 south to I-270 east and S.R. 315 north to I-270 west with flyover ramps that reduce almost 80 percent of weaving and merging at the interchange.

Loop ramps located in adjacent quadrants at an interchange cause intense weaving because motorists exiting and entering a highway must share a lane. As traffic volume grows higher at the interchange, this weaving leads to congestion and accidents. Flyover ramps reduce weaving and accommodate higher speeds by separating different traffic movements and flattening curves. Loop ramps have tighter curves and slower design speeds.

Other improvements include:

  • Improving the safety of the I-270 ramps to S.R. 315 south by flattening the curve to better accommodate high-speed travel. The lane configuration would also be changed to eliminate merging at the ramps before joining S.R. 315.

  • Creating dedicated lanes and ramps that separate through traffic on I-270 east from ramp traffic to and from S.R. 315 and U.S. 23.

Not Recommended: ODOT also analyzed a similar concept called Alternative 2, which would replace the same loop ramps using a different flyover ramp design with more sweeping curves. This concept operated equally well compared to Alternative 1, but it was more costly and time consuming to build, and had more environmental impacts.

 

U.S. Route 23 Interchange
Recommended: Replace exit "loop" ramps with a ramp design that brings traffic to a signalized intersection.

ODOT recommends Alternative 1, which would reduce nearly 90 percent of the weaving and merging by replacing the exit ramps from I-270 west to U.S. 23 south and I-270 east to U.S. 23 north. Instead, the ramp design would eliminate the loops and bring traffic to a signalized intersection on U.S. 23. The ramp design would be similar to the Sawmill Road interchange, except there would be two signalized intersections instead of one.

Other improvements include:

  • Reduce weaving and merging between U.S. 23 and S.R. 315 by creating separate ramps for U.S. 23 traffic to I-270 west and S.R. 315.

Not Recommended: ODOT also analyzed a similar concept called Alternative 2, which would replace the entrance loop ramps from U.S. 23 to I-270 with a directional ramp that merges with oncoming traffic. This concept is not recommended because it would not reduce weaving and merging, which contributes to congestion and accidents.

 

U.S. Route 23 North
Recommended: Separate through and local traffic by creating northbound express lanes down the center of U.S. 23

The U.S. 23/I-270 interchange cannot be fixed without addressing the bottleneck on U.S. 23 north of the interchange. ODOT recommends Alternative C, which would eliminate all weaving and merging by separating through and local traffic. In addition, the design would accommodate future traffic growth well beyond 2028.

The concept would construct two through lanes northbound in a trench down the center of U.S. 23, which would allow traffic to bypass signalized intersections. Two lanes for local traffic would be maintained on the outside, with caps at the intersections for turn lanes.

Not Recommended: ODOT also analyzed two other alternatives. Alternative D would separate through and local traffic by placing through traffic on elevated structures through the corridor. The design is not recommended because it would require multi-span bridges and piers, which would complicate turning movements and reduce sight distance.

In addition, ODOT analyzed Alternative A, which would add an additional lane in each direction on U.S. 23. This design was not recommended because it would not reduce merging and weaving on U.S. 23, which contributes to congestion and accidents.

 

Interstate 71 Interchange
Recommended: Replace the "loop" ramp from I-270 east to I-71 north with a flyover ramp.

Replacing the ramp will eliminate 100 percent of the weaving and merging and nearly all of the congestion at the interchange.

Other improvements include:

  • Improving the safety of the I-71 ramps to I-270 west by flattening the curve to better accommodate high-speed travel. The lane configuration would also be changed to eliminate the inside merge as the ramp joins I-270.

  • Increasing the capacity of I-270 west to I-71 north by widening the ramp to two lanes.

 


IV. What's Next?

ODOT will continue to solicit public input on these recommendations over the next month. Final recommendations will be made in March.

The preferred alternatives will then advance to further preliminary engineering and environmental screening, before moving to detailed design and construction. The estimated cost of construction is between $150 and $200 million. Construction on the I-71 interchange could begin as early as 2006. Construction on the S.R. 315 and U.S. 23 interchanges and U.S. 23 north could begin in 2008.

 

Preliminary Concepts Alignment Presentation (Aerial Views) :  
Small 1.69 MB PDF or  Large 19 Mb PDF

 

 I-270 Columbus North Central Outerbelt Study

 

Columbus Crossroads, ODOT I-70/I-71 South Innerbelt Study
T h e   O h i o   D e p a r t m e n t   o f   T r a n s p o r t a t i o n   ( O D O T )

Ted Strickland, Governor | James G. Beasley, P.E., P.S., Director
Privacy Statement | Feedback