PROGRAM MANAGER
LIST AND CHANGE ORDER THRESHOLDS
Office of
Construction Administration
|
CHANGE ORDER
THRESHOLDS FOR CENTRAL OFFICE FUNDED PROGRAMS CONSULT BY E-MAIL PRIOR TO WORK OR APPROVAL |
|||
|
Group ID |
Program |
Manager |
Thresholds |
|
SAC Codes |
|
(all 614 area code
except as noted) |
$ and/or % |
|
MNC 4BK7,
4BD7, 7BDB, 7PE7, 729B, 727B, 4D27, 4EK5, 7287, 4EK7, 7307, 729A, 727A,
4BD74MN7, 4J27, 4R27, 4D47 |
Major New Construction |
Jennifer Townley 466-7493 Don Fisher (614) 387-2614 |
$100,000 and all CO’s
after project price has increased 10% |
|
|
|
|
|
|
APD 4D27, 4D37 |
Major & New Construction Other |
Jerry Workman (614) 387-5417 |
$100,000 and all CO’s after project price has increased
10% |
|
|
|
|
|
|
GSP 4F27, 4F37, 4665 |
Grade Separation Program |
Tony Goddard 752-9005 Rich Behrendt (614) 387-3097 |
$50,000 and all CO’s has increased 10% |
|
|
|
|
|
|
MBP 4BU7, 4BT7, 7BTB |
Major Bridge Program |
Kelly Brooker Scocco (614) 387-6225 |
$100,000 and all CO’s after project price has increased
10% |
|
|
|
|
|
|
MLR 4RC7, 4RA7, 7RAB, |
Multi-Lane Reconstruction |
Scott Phinney (614) 644-9147 |
$100,000 and all CO’s after project price has increased
10% |
|
|
|
|
|
|
ABP 4BQ7, 4BS7 |
Amish Buggy Program |
Jerry Workman (614) 387-5417 |
$10,000 |
|
|
|
|
|
|
4B47, 4BX7 |
Miscellaneous Statewide Program |
Julie Ray (614) 466-2687 |
$15,000 |
|
|
|
|
|
|
4BY7, 4BE7 |
Emergency Capital |
Rich Winning (614) 644-5424 |
Make contact on ALL change orders |
|
|
|
|
|
|
TEA 4B37 |
Trans. Enhancement Bikeways |
(614) 644-8211 |
If over Funding Cap. If no Funding Cap, then Lesser of $10,000 or 10% of
original contract price |
|
|
|
|
|
|
HSP 4BJ7, 4BC7, 4DP7, 4BCB, 718B, 4BJ2, 7197, 718A, 4BC2,
7BC7, 4RS7, 4HJ7, 4R67 |
Safety |
Michelle May (614) 644-8309 |
$50,000 and all CO's after project price has increased 10% |
|
|
|
|
|
|
NWR 4BV7 |
Retrofit Noise Walls |
Elvin Pinckney 466-5154 |
5% of noise wall portion of project price |
|
|
|
|
|
|
RAS 4BP7, 4BR7 |
Rest Areas |
Mark Spagnuolo 752-0388 |
Lesser of $10,000 or 10% of original contract price. |
|
|
|
|
|
|
LBR 4HC7 |
|
(614) 644-8211 |
If over Funding Cap. If no Funding Cap, then Lesser of $10,000 or 10% of
original contract price |
|
|
|
|
|
|
CBR 4R87 |
City Local Bridges |
(614) 644-8211 |
If over Funding Cap. If no Funding Cap, then Lesser of $10,000 or 10% of
original contract price |
|
|
|
|
|
|
STM 4B97 |
|
(614) 644-8211 |
If over Funding Cap. If no Funding Cap, then Lesser of $10,000 or 10% of
original contract price |
|
|
|
|
|
|
4D57 |
Discretionary |
Linda Bailiff (614) 728-8062 |
All funds are capped. |
|
|
|
|
|
|
GSM 4SF7, 4SS7 |
Geologic Site Management (landslides) |
Jerry Workman (614) 387-5417 |
$50,000 and all CO's after project price has increased 10% |
|
|
|
|
|
|
CHANGE ORDER
THRESHOLDS FOR CENTRAL OFFICE FUNDED
PROGRAMS WITH
INTERNAL AND EXTERNAL MANAGERS CONSULT THE EXTERNAL MANAGER BY E-MAIL PRIOR TO WORK OR APPROVAL AND COPY INTERNAL MANAGER |
|||
|
MTP 4BW7 |
Metro Parks |
External
Manager: Don Osborn (614) 839-6225 Fax (614) 895-3050 dosborn@apraonline.org Internal
Manager: Sharon Todd 614-752-4685 |
All CO’s after project price has increased 5% |
|
|
|
|
|
|
DNR 4BF7 |
ODNR |
External
Manager: Ohio Department of Natural Resources (ODNR) Gus Smithhisler (ODNR) (614) 265-6965 paul.smithhisler@dnr.state.oh.us Internal
Manager: Mike McColeman 614-644-7155 |
All CO’s $25,000 or greater |
|
|
|
|
|
|
LRS 4B77, 4HB7, 4RB7 |
County STP Program |
External Manager: Michele Risko (614) 221-0707 X15 Internal Manager: |
All CO’s after project price has increased by: 10% for
project under $1 million 5% for projects of $1 million and over |
|
|
|
|
|
|
LBR 4B87 |
|
External Manager: Michele Risko (614) 221-0707 X15 Internal Manager: |
All CO’s after project price has increased by: 10% for
project under $1 million 5% for projects of $1 million and over |
|
|
|
|
|
|
LOM 4TA7, 4TB7, 4TC7, 4AQ7, 4AM7 |
Local MPO |
External Manager: Local MPO contact person Internal Manager: Dave Moore (614) 466-0754 |
All CO’s
after project price exceeds funding CAP are 100% local participating agency
(city, village, county, or township) not the MPO, inform the appropriate
agency when this occurs. |
|
|
|
|
|
|
SPECIAL
FUNDS MANAGED BY ROD
RICKABAUGH (614)
752-2179 |
|||
|
4BG6 |
OPWC Local Government Projects |
There is no
need to contact the Program Manager, Rod Rickabaugh (614) 752-2179, if the
Memorandum of Funds for the project gives a funding CAP. Any change order
increasing the project above this CAP is 100% District or locally funded. You
should advise the District Planning and Programming Administrator or local
agency when this occurs and inform them that they must fund the change order
from another source. |
|
|
4BG7 |
Local Government Projects |
||
|
4D47 |
Major and New Construction (Discretionary) |
||
|
4J27 |
Major and New Construction (Demo) |
||
|
4J37 |
District Demonstration |
||
|
4J47 |
Local Government Demonstration |
||
|
4J57 |
Other Demonstration |
||
|
4RD7 |
High Priority Projects |
||
|
4R27 |
Major and New Construction (High Priority) |
||
|
4R37 |
District High Priority |
||
|
4R47 |
Local Government High Priority |
||
|
4R57 |
Other High Priority |
||
|
|
|
|
|